Description

Project: The refurbishment of the roofline including the fascia’s . soffits, guttering and downpipes and to

include the stripping and safely storing for reuse the courses of tiles required to replace the 1st row of

felt and batten including rafter roll and eaves support trays. Supply and install 300mm of insulation to

the roof space above the communal stairwell.

• NB: All roofing work to be carried out by an NFRC accredited contractor

• As part of contractor pre-survey, contractor should identity any soffit and live extractor fan vents

which will need to be disconnected and reconnected during works

• All flats must be checked to see if there are any live gas appliances, wood burning/multi fuel

stoves or open fires still in use prior to the removal of any chimney stacks. Evidence shall be

provided to the Aster Surveyor who will be able to authorise this phase of work if necessary.

Isolation of flues (priced separately) in line with gas protocols, removals (priced separately) to

be discussed and review with client.

• Aster Surveyor to advise with any blocking up and venting work as the scope of work will need

to be agreed with the leaseholder/s or resident/s in advance.

• Erect tubular steel scaffolding with required lifts to such elevations, including suitable access for

removing the shared chimney and dismantle on completion. All scaffolding to be measured

against the face of the building and to include the lift heights for a specific work type and trade.

Page 5 of 15

• Remove existing tiles and safely store for reuse, remove battens, felt from the eaves course and

safely lower to ground level and remove from site.

• Allow for clearing all debris from the eaves and, then insulate using a 50-75mm thick PIR

insulation board with a foil backing ensuring that an adequate air gap's left for ventilation.

• Supply and fix new Permavent Apex breathable membrane to the cleared area area and fix new

38 x 25 mm tanalised timber battens to rafters. Reinstate the stored tiles.

• Supply and fix eaves support trays G1281 by Manthorpe, including rafter roll fitted as per

manufacturer’s instructions. To all roofs in contract.

• Allow for supplying and fitting new deep flow guttering including downpipes, connections and

associated fixtures & fittings to flat block.

• Allow for supplying and fitting uPVCu fascia's, soffits.

• Test guttering for leaks and adequate falls. Deliver free of dirt or imperfections. All waste

material and debris will be removed from site.

• Supply and lay 300mm of mineral wool insulation to the roof space above the communal

stairwell

• The contractor is to leave the properties and surrounding areas etc clean and clear to original

condition. Wash down windows, doors, and existing/new PVCu Fascia's/soffits on completion to

remove dirt & debris caused by roofing works.

The rest of this notice

The tender documents, the buyer's named contact, the award history and our AI analysis for this notice are part of Pro. Start a free trial to open the full record.

  • Download the tender documents
  • Contact the buyer directly
  • See who won, and for how much
  • Read the AI analysis of scope and risk
  • Get alerts for tenders like this one
Start your free trial

14 days free. No card required.

Guides for bidders

New to public sector tendering? These short guides explain how the process works.